A defensible method for technical and commercial bid comparison
Who this guide is for: project owners, procurement leads, EPC tender committees, technical advisers and project management consultants evaluating industrial and infrastructure contracts in the UAE and wider GCC.
A tender comparison is not a ranking of submitted lump sums. The objective is to identify the proposal offering the best outcome against a documented evaluation method, after removing differences in scope, commercial assumptions and technical compliance. On a storage terminal or other process facility, an apparent saving may be offset by excluded piling, utility connections, interface works, commissioning obligations or programme conditions.
1. Establish the rules before opening financial offers
Agree a tender evaluation plan before reviewing commercial bids. It should record the mandatory pass/fail requirements, approved technical criteria and their scoring anchors, financial normalization rules, schedule treatment, tax and currency basis, clarification protocol, approval authority and requirements for an auditable evaluation record. Where a regulated procurement framework applies, the published bidding documents govern; this article is not a substitute for those rules.
Different evaluation methods answer different questions. A lowest evaluated cost approach requires price to be adjusted onto a comparable basis. A weighted rated-criteria approach explicitly trades documented non-price attributes against evaluated cost. Do not silently change criterion weights because a favored bidder scores poorly.
2. Separate responsiveness from merit
The first gate asks whether the offer is responsive to material tender requirements. Examples include a binding offer from the intended contracting entity, required securities or guarantees, acknowledgment of governing contract terms, acceptance of testing and commissioning obligations, required experience and proof of safety-critical capability. A material failure must be assessed according to the tender rules; a high technical score cannot automatically cure it.
For responsive offers, score technical merit using evidence rather than general impressions. A typical breakdown for a process-plant EPC tender might allocate 30% to technical solution and FEED endorsement, 20% to execution methodology, 20% to relevant delivery capability, 15% to schedule credibility, and 15% to HSE, QA/QC and commissioning arrangements. These are illustrative internal technical allocations, not a universal standard. Each criterion requires a defined scale, such as 0 (absent), 50 (partially substantiated), 75 (credible), and 100 (fully demonstrated against the stated requirements).
3. Normalize bids onto one commercial scope
First document each bidder’s submitted price, then build a reconciliation to the evaluated price. Common adjustments may include:
- Correcting tender arithmetic under the stated evaluation rules.
- Pricing owner-retained works and bidder exclusions needed to deliver the same scope.
- Normalizing supply boundaries, approved alternates and provisional allowances.
- Applying unconditional discounts consistently.
- Converting currencies at the exchange rate and date stated in the tender documents.
- Applying recoverable and non-recoverable tax treatment consistently, without double counting.
Keep a separate register of qualifications that cannot reasonably be converted to a firm value: for example, undefined geotechnical risk, unverified utility supply, unclear fitness-for-purpose obligations or an unachievable interface milestone. An unpriced major exposure should be explicitly escalated rather than disguised inside a score.
4. Worked example: the lowest submitted bid is not necessarily the best evaluated bid
All bidder names, amounts and scores below are invented to demonstrate the method. They are not actual UAE tender prices.
| Bidder | Submitted EPC price (USD m) | Priced scope adjustments (USD m) | Evaluated price (USD m) | Technical score /100 |
|---|---|---|---|---|
| A | 42.00 | 3.00 | 45.00 | 82 |
| B | 45.00 | 0.50 | 45.50 | 92 |
| C | 47.00 | 0.00 | 47.00 | 88 |
On smaller screens, review each row in card format.
Assume all three have passed the mandatory compliance gate, the approved technical weighting is 55%, and evaluated price has a 45% weighting. For a positive-cost criterion, the normalised price score is:
Price score (%) = (lowest evaluated price / bidder evaluated price) × 100.
Weighted total = (technical score × 0.55) + (price score × 0.45).
| Bidder | Price score /100 | Weighted technical | Weighted price | Total /100 |
|---|---|---|---|---|
| A | 100.00 | 45.10 | 45.00 | 90.10 |
| B | 98.90 | 50.60 | 44.51 | 95.11 |
| C | 95.74 | 48.40 | 43.09 | 91.49 |
On smaller screens, review each row in card format.
Under these assumed and pre-approved weights, Bidder B ranks first despite not offering the lowest evaluated price. Its higher evidence-based technical score outweighs the modest evaluated-price difference. This is a calculated ranking, not an automatic award recommendation: compliance, clarification closure, counterparty capacity, schedule risks and approval conditions still matter.
Do not confuse price score and price premium. The price score is capped at 100 for the lowest bid. Price premium is the amount above the lowest price: for Bidder B, (45.50 / 45.00 − 1) × 100 = +1.11%. A premium can exceed 100%; a properly normalized ratio score should not.
5. Schedule and delivery risk require separate evidence
An EPC offer of 30 months and another of 36 months are not directly comparable unless both use the same start event, access assumptions, engineering and authority milestones, jetty/interface readiness, mechanical completion definition, commissioning activities and acceptance criteria. A contractor’s promise to accelerate only after award is not a baseline. Ask for a critical-path schedule, procurement lead times, quantified recovery measures and interface constraints. If schedule is a scored criterion, publish how the difference affects points.
6. Document clarification outcomes and residual conditions
Maintain a controlled clarification log with reference number, issue, bidder response, employer decision, commercial effect, technical effect, status and evidence. Do not treat an offered value-engineering saving as an unconditional discount unless scope, performance, approval requirements and timing are contractually defined. Treat conditional exclusions, subcontractor substitutions and post-award FEED gap analyses as decision risks.
The evaluation report should contain (i) compliance assessment, (ii) normalized price bridge, (iii) technical scoring sheets, (iv) schedule comparison, (v) risk register, (vi) ranked results, (vii) dissenting observations and (viii) proposed award conditions. Preserve bids and versions so the committee can reproduce the outcome.
7. Practical evaluation checklist
- Is the contracting entity and responsible EPC counterparty identified?
- Are the FEED assumptions and equipment battery limits aligned?
- Have civil, piling, utilities, permits and third-party interfaces been allocated?
- Are FAT, SAT, commissioning, performance tests and acceptance included?
- Are exclusions priced or clearly treated as unresolved risk?
- Is the schedule measured from the same contractual trigger?
- Are scores and weights traceable to pre-established criteria?
- Does the final recommendation distinguish evaluated cost from submitted price?